Groundbreaking for new playground to include 2 basketball courts, four square, pickleball courts and a sheltered pavilion. Present for the groundbreaking were (left to right) Board of Education Vice President Scott Kral, President Matthew Trawinski, Trustee Teresa Judge Cravello, School Superintendent Sue DeNobile, Business Administrator Cheryl Jiosi
For new parking lot layout click here: Parking Lot
For new playground and basketball court layout click here: Basketball Court
UPDATE: August 05, 2022
Tree removal took place on August 5, 2022 to clear the area for the construction of the new basketball, four square, and pickle ball courts
Update: August 12, 2022
As of August 11, 2022 the recreation area is being leveled for the new courts, and the areas in need of new paving for the parking lot and the alleyway are all underway!
UPDATE: October 11, 2022
As of today, the phase of installing the top coating and lining the courts is in the works and we are nearing completion.
Update: October 21, 2022
Almost Finished
November 2, 2022