• Midland School Infrastructure
    Upgrade Schedule and Timeline

     
    School
     
    WINTER 2013-2014 AGENDA
    • Kick off meeting with school district to discuss project scope and scheduling
    • Asbestos and Environmental Testing 
    • Meeting with Building and Grounds Committee
    • Value engineering meeting with Fujitsu to discuss heat pump option
    • Meetings with Police and Fire Chiefs
    • Meeting with construction code officials

    SUMMER 2014 AGENDA

    • Asbestos abatement
    • Door replacements and access control
    • Roof replacement
    • EIFS replacement
    • Sprinkler upgrade
    FALL 2014 AGENDA
    • Toilet renovations Phase 1
    • Boiler Upgrades Phase 1
    • Window Replacement
    • AV/IT Security/Technology Upgrades
    SPRING/SUMMER 2015 AGENDA
    • Boiler Replacement Phase 2
    • Toilet Renovations Phase 2
    • Brick repointing
    • Lighting and ceiling upgrades